Lambeau Field Redevelopment Project - $ 295,000,000

January 2001 - October 2003

by Michael J.Constantini -  Director of Field Operations


The project consisted of 1,700,000 S.F. of new and renovated spaces including:

Renovation/Expansion of Existing Stadium Structure

  • New stadium perimeter structure including lower and upper concourses

  • New press-box level including cafeteria

  • Locker room and training facilities

  • 3,000 Indoor Club Seats

  • 3,200 Outdoor Club Seats

  • 174 Luxury Suites

  • New men's and women's rest room facilities:  Increase in women's rest rooms from 180 to 600+ and men's from 436 to 550+

  • More than 340 Point of Sale Locations for Vendors

  • Outdoor plaza with 20 foot bronze statues

  • Parking lot renovations   

New Five Story - 360,000 S.F. Atrium 

  • Packer Hall of Fame

  • 11,500 S.F. Packer Pro Shop

  • Fan Zone

  • Restaurants

  • Banquet Facilities

  • Retail Space

  • Administrative Offices

Responsibilities included:

  • Coordinated over 60 subcontractors which consisted of 1200 workmen during the peak of the schedule.

  • Directed site safety and security, which was critical through three seasons of NFL football games.

  • Coordinated public safety efforts around Lambeau Field after the 9/11 disaster.  Worked closely with Green Bay police and fire departments as well as the NFL to assure public safety during game days.

  • Met aggressive 33-month schedule on time and within budget.

 